District Energy

City of Vancouver NEU Southeast False Creek DPS & ETS Expansion

Key Details

Owner:

City of Vancouver

Mechanical Consultant:

Kerr Wood Leidal Associates Ltd.

General Contractor:

Division 15

Project Delivery:

Bid Spec

Date Project Finished:

2018

This project saw the fabrication of Division 15’s first skid-mounted ETS system, which was constructed at Division 15’s fabrication facility and shipped as a complete package for installation.

Division 15 connected new buildings to South East False Creek's Neighbourhood Energy Utility (NEU) by extending the distribution network piping through building parkades and tying into the building Energy Transfer Station (ETS), complete with system shutdown in coordination with NEU operation staff. The distribution piping system project consisted of the installation of an underground network of pre-insulated thin-walled steel pipes, as well as parkade piping running to each building’s mechanical room.

The Energy Transfer Station (ETS) portion of the project consisted of the fabrication of nine energy transfer stations, providing heat to new residential and institutional developments. This project saw the fabrication of Division 15’s first skid-mounted ETS system, which was constructed at Division 15’s fabrication facility and shipped as a complete package for installation in each building.