Key Details
Owner:
Simon Fraser University Facilities Services
Mechanical Consultant:
Kerr Wood Leidal Associates Ltd.
General Contractor:
Ledcor Construction Limited
Project Delivery:
Lump Sum
Date Project Finished:
October 2022
About The Project
Division 15 installed the District Energy piping for the heating system at Simon Fraser University, including the installation of around 160m of 10” and 16” welded pre-insulated steel hot water pipes connecting to the existing SFU district energy system. This installation includes a branch connection to a residential/office building.