District Energy

False Creek Energy Center Low Carbon Expansion

Key Details

Owner:

The City of Vancouver

Mechanical Consultant:

Kerr Wood Leidal Associates Ltd.

General Contractor:

Scott Special Projects Ltd.

Project Delivery:

Lump Sum

Date Project Finished:

October 2024

Awards:

2025 Awards of Excellence Nominee

The False Creek Energy Centre previously had one 3 MW heat pump that recovered heat from sewage to provide space heating and hot water to buildings connected to the Neighbourhood Energy Utility. The Low Carbon Expansion project scope included two additional 3.3 MW heat pumps to recover additional heat from sewage.

Division 15’s scope was installation of 18” welded sewage piping within the facility connecting the new heat pumps to the forcemain complete with screening units and pumps and 10” fully welded district energy piping complete with distribution pumps as well as refrigerant, vent, and drain piping.